NZTA Subsoil Drainage – Ventia

October 2025 – January 2026

Client: Ventia (for NZTA)

Location: State Highway 1

Overview: SBA Civil was engaged to deliver an accelerated subsoil drainage installation within live traffic conditions on State Highway 1, requiring precise staging, continuous operations, and rigorous safety management. 

Scope of Works: 

  • Installation of approximately 4,500 metres of inground subsoil drainage 
  • Delivery across two work fronts averaging around 400 metres per day 
  • Traffic staging and management to maintain live highway operations 
  • Four full road-closure weekends to complete critical road crossings 

Challenges & Approach: Works were undertaken under an intensive seven-day programme, operating split shifts of 15–16 hours per day over a four-week peak delivery period. Detailed planning and disciplined traffic management ensured safety and minimal disruption to the travelling public. 

Outcome: The drainage works were completed efficiently within the accelerated timeframe, demonstrating SBA Civil’s capability to deliver high-volume infrastructure works safely within live state highway environments. 